29 Oct 18:54
start dates disappear and predecessor ignored when I re-open file
Greg McAvoy-Jensen <gregmj <at> sbcglobal.net>
2003-10-29 17:54:36 GMT
2003-10-29 17:54:36 GMT
Greetings,
Thank to the developers and those on the list who've helped make this
product. I find it extremely helpful. But I have had one difficulty:
I have a project with many links. The task list includes two sets of
subtasks, and it's those which get confused. When I re-load the program,
their predecessor seems to be ignored, and on the Gantt chart they show
up far to the left. Their start date, normally in 2004, shows January 1
1970, though it's categorized as ASAP.
The correct the problem, each time I load the file I have to delete
those predecessors and add them again.
I'm running 0.10 on Red Hat 9. I had the problem on 0.9.1, too--same
file. It's pasted below. Thank you for any help anyone can provide.
Peace and all good,
Greg McAvoy-Jensen
------------------
<?xml version="1.0"?>
<project name="Build Sacramento Cohousing" company="Sacramento Cousing" manager="" phase="Forming
a Group" project-start="20000201T000000Z" mrproject-version="2">
<properties>
<property name="cost" type="cost" owner="resource" label="Cost" description="standard cost for a resource"/>
</properties>
<phases>
<phase name="Forming a Group"/>
<phase name="Acquired Land"/>
<phase name="Building"/>
(Continue reading)
How do I set this kind of things in MrProject?
Version information: mrproject 0.9.1 on Debian/powerpc "testing".
I thank you very much,
Giuseppe Sacco